EV charging station requirements were to be included with other building code updates associated with an all-electric reach code. These amendments were initially planned for 2023, but the successful lawsuit by the California Restaurant Association in January 2024 overturning natural gas bans has caused the City to revise the code updates.

Official description

Amend the building code update to expand EV charging stations requirements for multi-family and non-residential properties
(Full action name in the CAP)

Description

The City has been working to amend the building code to expand EV charging requirements.

Tasks

What are we doing?

  • Todo2024

    Complete and adopt amended building code

Interdependent actions

Summary and contacts

  • Council Prioritization Score

    69.4

Action Timing

Reduce GHG Emissions

Community Identified Action

  • Feasibility score

    7.93(1-10)
  • Equity score

    5.5(1-10)
Information updated 09/11/2024